What Caltrans Has Planned for Corte Madera's Tamalpais Drive Bridge Over 101

What becomes of the two spiral walkways at Tamalpais Drive? Anyone who has walked from the Old Square side of Corte Madera to Town Center, or caught a bus on the freeway shoulder below, knows them. They are the curling concrete ramps that take pedestrians from bridge level down to the paths under the overcrossing and to the bus stops on the loop ramps.

Under the design Caltrans has selected, both spirals come out. So do the bus stops they lead to. Caltrans's current schedule puts the start of construction in the spring of 2028, so the crossing as you know it will stay in place for a while yet. Each part of the plan changes something specific about how you get from one side of town to the other.

The Bridge as It Works Today

Highway 101 splits Corte Madera roughly down the middle. The town's General Plan names only three places to cross it: the Tamalpais Drive interchange, the Wornum Drive underpass, and a pedestrian overcrossing north of Wornum Drive. Town Hall, Town Park and the Post Office are all on the west side. The Village and Town Center shopping centers are on the east.

That makes Tamalpais Drive the most central of the three, and it was built mainly for cars. Caltrans's own project documents describe it this way:

  • One sidewalk, on the eastbound side of the bridge.
  • Two spiral walkways connecting the bridge to the paths below and to the bus stops at the loop ramps.
  • No designated bike lane, so cyclists either share the right lane or ride on the sidewalk.
  • Bus bypass stops on the northbound and southbound on-ramps, plus eastbound and westbound stops on the overcrossing itself.

Caltrans also says the sidewalks and curb ramps across the overcrossing don't meet ADA standards. The structure itself needs work too. The bridge's last cited inspection report, from May 2016, noted that its existing system can't be fully inspected, and that is the main reason the project includes a seismic retrofit.

What Alternative 4B Swaps Out

Caltrans chose a design called Alternative 4B. It keeps the bridge where it is and rebuilds almost everything a person on foot, on a bike or waiting for a bus would touch. The project's 2026 baseline agreement with the California Transportation Commission lays it out.

Piece of the crossing Today Under Alternative 4B
Ramps from bridge level Two spiral walkways Spirals removed, two new pedestrian ramps built
Bridge deck One sidewalk, eastbound side Bridge widened
Southwest corner Existing intersection New pedestrian and bike sidewalk toward Casa Buena Drive
Bikes No designated lane Class II bike lanes, two bike boxes, six green conflict-zone markings
Freeway on- and loop-ramps Free-flowing loop ramps Reconfigured as signalized intersections
Bus stops Bus bypass stops on the ramps Existing bypass stops removed, new bus stop and pullout at the southbound off-ramp

The bike lanes are shorter than many people might expect. Caltrans lists 160 linear feet of Class II lanes, which fits a project focused on getting across the interchange. The same document counts 12 ADA-deficient elements to be fixed and two transit stops to be improved.

The signals matter most for people on foot. When loop ramps become signalized intersections, a pedestrian crossing at a ramp gets a light to cross with, which they don't have at a free-flowing ramp. The plan pairs that with the new sidewalk toward Casa Buena Drive, the street that runs along the freeway on the west side.

Bus Riders Feel the Change First

Marin Transit's Route 71 timetable for September 2026 shows southbound buses toward Marin City stopping at the "Hwy 101 @ Tamalpais Dr Bus Pad" about every half hour on weekdays. Northbound Route 71 buses stop at the "Hwy 101 @ Paradise Dr Bus Pad" across the freeway.

Route 17, which runs between downtown San Rafael and Sausalito by way of Mill Valley, uses the same pair. It stops at the Tamalpais Drive pad southbound and the Paradise Drive pad northbound, and the northbound trip continues to Larkspur Landing.

Golden Gate Transit's April 2026 transit guide lists its Route 132 at the Paradise Drive Bus Pad, which it locates on Highway 101 at Paradise Drive and Tamalpais Drive.

Alternative 4B removes all of the existing bus bypasses and stops at the interchange. It adds a new bus stop with its own pullout where the southbound off-ramp is widened. For riders, getting to the bus is the part that changes. Today it means a walk down a spiral. After the rebuild, the stop sits at a signalized ramp intersection.

Until then, the pads work as they always have, and the route pages above show current times at each stop.

A Calendar Measured in Seasons

The start date has moved more than once. In October 2025 the Marin Independent Journal reported that the upgrades had been postponed until 2027 because a PG&E transmission line needed to be relocated. A month later, Town staff told Corte Madera's Bicycle and Pedestrian Advisory Committee that Caltrans had delayed the project to 2028, according to the committee's November 10, 2025 minutes.

A Caltrans District 4 status memo dated January 22, 2026 lists the current targets:

  1. July 5, 2027: right-of-way certification.
  2. July 30, 2027: ready to list the project for bids.
  3. April 3, 2028: contract approval, the milestone Caltrans uses to mark the start of construction.

The 2026 state highway program has $55.899 million set aside for the remaining phases. Caltrans puts the full project at $58.339 million when the completed environmental phase is counted. Caltrans is the implementing agency and will build it. The Town of Corte Madera and the Transportation Authority of Marin are among the funders.

If those dates hold, this winter and the next both pass with the spirals in place, and crews arrive in spring 2028.

Crossing 101 Until Then

For now, Tamalpais Drive stays the central crossing, and the other two General Plan crossings are worth knowing for trips that don't need it. The Wornum Drive underpass is the southern alternative. The pedestrian overcrossing north of Wornum Drive is the one with no car traffic.

The overcrossing also links to some of the best walking and riding near the Larkspur line. The Metropolitan Transportation Commission's Bay Trail guide for central San Rafael to Corte Madera describes the route this way:

  • A bike and pedestrian greenway path across Corte Madera Creek between Redwood Highway and Sir Francis Drake Boulevard.
  • A path over the creek beside the freeway, reached by turning right just before the Marin Rowing Association boathouse.
  • The bike and pedestrian overcrossing back to the east side of the freeway, then Redwood Highway to the shoreline path at Redwood Highway and Wornum Drive.
  • Muzzi Marsh, part of the Corte Madera Marsh Ecological Reserve, along the shoreline.

The same guide warns that Paradise Drive south toward Tiburon has no sidewalks and only a minimal shoulder. It isn't recommended for pedestrians or for inexperienced cyclists.

People who bike from the east side to Town Park, including those coming for the lunch trucks we wrote about in Corte Madera's park food truck coverage, can pick the crossing that suits the trip. Tamalpais Drive is the direct route. The Wornum-side crossings trade some distance for a calmer ride.

What the Work Will Look Like

When construction starts, Caltrans expects it to last 360 to 480 working days. Crews will work day and night shifts depending on the task. The plan relies on lane and shoulder closures, temporary ramp closures and detours, and temporary concrete barriers. Caltrans states that no prolonged ramp closures are needed.

The project's traffic management plan is estimated at $865,000. It includes a public information program, portable changeable message signs, flaggers, and a California Highway Patrol enforcement program for work zones during lane and ramp closures. Detailed closure notices will come from that plan once construction is scheduled.

The Town keeps a project page for the Tamalpais Drive overcrossing, and that is the place to watch for updates as the 2027 milestones approach.

We follow how changes like this shape daily life on both sides of 101, from the bus stops by the spirals to the walk to Town Park. If you'd like to talk through how the Tamalpais Drive timeline fits your plans in Corte Madera, McArthur Love Team is glad to help, and our Corte Madera neighborhood page is a good place to start.